Comet Gold Mine Restart Activities Accelerate
Released
Released
Announcement PDF
Valiant Gold Limited (ACN 691 820 532)
A: Ground Floor, 34 Colin Street West Perth WA 6005 | W: www.valiantgold.com.au
ASX ANNOUNCEMENT
2 SEPTEMBER 2026
COMET GOLD MINE RESTART ACTIVITIES
ACCELERATE
Valiant Gold Limited (ASX: VAL) (Valiant or the Company) is pleased to provide an operational
update on activities supporting the restart of its 100%-owned Comet Gold Mine in Western
Australia’s Murchison region.
The favourable underground conditions encountered during the successful re-entry of Comet
in July have provided Valiant confidence to accelerate critical restart activities. Bringing forward
major infrastructure, procurement and technical workstreams is expected to shorten the
pathway to restart readiness, with execution progressing in parallel with completion of the
Comet Restart Study.
Key Highlights
Power contract awarded - Site power station and underground electrical infrastructure
ordered, with delivery scheduled for Q2 FY27.
Primary ventilation equipment ordered - with installation and commissioning
scheduled for Q2 FY27.
Scalable camp contract awarded – initial 30-room camp to be installed in Q2 FY27.
Dewatering infrastructure advancing - Permanent pumping equipment and additional
dewatering equipment ordered, with network installation progressing.
Communications and safety infrastructure progressing - Underground refuge
chambers ordered and communications infrastructure installed and commissioned.
Underground drilling tender commenced - Tender process underway for priority grade
control and resource definition drilling, with commencement targeted for Q2 FY27.
Comet Restart Study advancing - Detailed mine planning and pricing continuing in
parallel with completion of the Comet Restart Study targeted for Q2 FY27.
Management Comments
“Valiant is advancing the critical infrastructure, site and technical workstreams required to return
Comet to production. Completion of the Comet Restart Study, targeted for Q2 FY27, will provide
the basis for announcing the preliminary restart mining schedule and key milestones toward the
recommencement of operations. I look forward to providing further updates as each of these
exciting milestones is reached and mining commences”
Brendan Tritton, Managing Director & CEO
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 2
Comet Gold Mine Overview
The Comet Gold Mine is located within Valiant’s Comet Gold Project in the Murchison region of
Western Australia, only 14 km by road from Westgold Resources Limited’s Tuckabianna Mill and
110 km from the Bluebird Mill via the Great Northern Highway (Figure 1). The mine trend hosts
an existing Mineral Resource Estimate (MRE) of 3.77Mt @ 2.51g/t Au for 304koz of gold1
(Figure
2), providing a strong foundation for the restart of underground mining operations.
Following successful underground re-entry in July 2026, inspections identified lower-than-
expected water levels, generally dry workings, serviceable infrastructure and limited
rehabilitation requirements in the first potential production zones. These findings have informed
the site establishment, dewatering, rehabilitation, engineering and mine planning activities now
underway.
Figure 1: Location of the Comet Project relative to regional processing infrastructure, including facilities contemplated
under the Ore Purchase Agreement with Westgold Resources.¹
1
Refer to the Company’s Prospectus dated 16 February 2026, as amended by the Supplementary Prospectus dated 20 February
2026 (together, the Prospectus) for further information regarding the Mineral Resource Estimates.
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 3
Figure 2: Comet Mine Trend schematic long section, facing west, showing the Mineral Resource Estimate, ounce-per-
vertical-metre distribution and previously mined volumes.¹
Table 1: Comet, Pinnacles and Comet North Mineral Resource Estimate (MRE)1
Operational Update
Power Supply and Underground Electrical Infrastructure
Silverstone Energy Pty Ltd has been engaged to supply and deliver the 6.1 MW site power station
for the Comet restart program. Design, certification and site-preparation activities are
progressing in parallel with procurement, representing another key step towards establishing
the infrastructure required to support the restart of operations at Comet. The power station is
scheduled for delivery and commissioning in Q2 FY27.
Ancillary underground electrical infrastructure, including substations, distribution equipment,
and dedicated starters for pumping and primary ventilation, has been ordered. Design and
installation planning for underground power reticulation is continuing alongside manufacture
and delivery activities.
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
Comet 151,971 3.54 17,296 248,294 3.63 28,978 262,580 2.99 25,242 662,845 3.35 71,392
Comet
North (OP)
- - - 433,822 2.47 34,451 160,809 2.06 10,650 594,631 2.36 45,118
Comet
North (UG)
- - - 19,093 3.44 2,112 269,013 2.31 19,979 288,106 2.39 22,138
Pinnacles 84,012 2.22 5,996 1,189,880 2.28 87,223 955,172 2.34 71,860 2,229,064 2.31 165,549
Total 235,983 3.07 23,292 1,891,089 2.51 152,764 1,647,574 2.41 127,731 3,774,646 2.51 304,197
Comet
Measured Indicated Inferred Total
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 4
Grade Control and Resource Drilling
The Company has commenced a tender process to appoint an underground diamond drilling
contractor at Comet. The program will focus on priority grade control and resource definition
drilling to support mine planning, Mineral Resource conversion and growth from established
underground platforms. Contractor evaluation is underway, with mobilisation and
commencement of drilling targeted for Q2 FY27.
Figure 3: Pinnacles-Comet Mine schematic cross-section showing the underground mine workings, Mineral Resource
Estimate outline and classifications, planned drill platforms, and priority grade control, resource conversion and resource
extension drilling areas.¹
Comet Restart Study
Mine engineering, design, pricing and planning activities are continuing in parallel with the
critical infrastructure, site and technical workstreams required to return Comet to production.
The Comet Restart Study, targeted for completion in Q2 FY27, will consolidate the mine plan,
execution requirements and sequencing for the restart, incorporating the outcomes of the
infrastructure planning, procurement and site activities currently underway.
Completion of the Study will provide the basis for the Company to announce a preliminary
restart mining schedule outlining the key milestones, indicative sequencing and anticipated
timing toward recommencement of operations.
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 5
Ventilation Infrastructure
Primary ventilation equipment has been ordered for the Comet and Pinnacles underground
workings. The package includes fan equipment and associated installation accessories for the
two underground ventilation circuits.
Installation planning is progressing, including assessment of the existing underground
ventilation infrastructure and the interfaces required for installation.
Delivery, installation and commissioning of the primary ventilation equipment are scheduled for
Q2 FY27.
Dewatering and Pumping Infrastructure
Permanent pumping equipment has been ordered as part of the planned dewatering system.
Associated supporting infrastructure has also been ordered, while installation of the physical
dewatering network continues.
A new discharge line has been installed from the pit floor to the surface, replacing previously
removed infrastructure and supporting the pumping arrangement being established at Comet.
Additional dewatering equipment has also been ordered to support pumping activities while
the permanent power and pumping infrastructure is established.
Initial Scalable Camp Contract Awarded
Quick Camps Pty Ltd has been engaged to supply and construct an initial 30-person
accommodation camp to support the proposed Comet restart, with delivery scheduled for Q2
FY27. The camp has been designed to be progressively scalable from 30 to 60, and ultimately to
100, as site activities and workforce requirements increase.
The initial installation will include kitchen and mess facilities sized to accommodate up to 100
persons, enabling future expansion of the accommodation capacity without requiring a
corresponding upgrade to these core facilities.
The staged development approach will provide accommodation and associated facilities for
personnel undertaking early works and restart activities, while retaining flexibility to support the
progressive build-up of the site workforce.
Temporary Workshop and Site Establishment
Preparation of the temporary workshop area is well advanced, with pad preparation and
levelling activities progressing. Related works include the preparation of supporting water
infrastructure, the organisation of pipe laydown areas, and the removal of redundant pipework
and materials from operating areas.
The temporary workshop will support maintenance, rehabilitation, and site establishment
activities as the restart program advances.
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 6
Communications and Underground Refuge Chambers
Underground refuge chambers have been ordered as part of the safety and emergency-
response infrastructure planned for the underground workings. Delivery coordination and
installation planning are progressing alongside the broader underground infrastructure
program.
Communications infrastructure for surface and underground has also been installed and
commissioned for the Comet site. The communications package will support on-site and
underground communications as rehabilitation and infrastructure establishment activities
progress.
Figure 4: Comet communications infrastructure
Pit Ramp, Site Access and Underground Rehabilitation
Pit ramp and site-access works are progressing. Activities include reinstatement of sections of
the ramp sprinkler system and removal of redundant infrastructure from operating areas.
Inspections undertaken as part of power-reticulation and underground-infrastructure planning
have identified targeted rehabilitation requirements within sections of the underground
workings. Scoping and planning for these works are progressing alongside preparations for
installation of underground electrical infrastructure.
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 7
Valiant’s Development Pipeline
Comet: Lead mine restart workstream, with critical infrastructure, site establishment,
dewatering, rehabilitation and technical activities advancing in parallel with completion of
the Comet Restart Study and development of the preliminary restart mining schedule.
South Emu–Triton: Future underground restart opportunity, with recent drilling and
technical work supporting future mine planning and a planned review of the scope and
requirements for potential dewatering.
Boomerang: Potential open-pit and underground development opportunity, with Resource
definition drilling underway and Resource-growth planning in progress.
No development decision has been made in respect of Boomerang or South Emu–Triton. Any future dewatering or development decision
will remain subject to technical review, approvals, funding, sequencing and other relevant considerations.
Looking Forward
Valiant’s immediate focus is to continue advancing the critical infrastructure, site and technical
workstreams required to return Comet to production, while completing the Comet Restart Study
and developing the preliminary restart mining schedule.
Comet Restart Study and preliminary mining schedule– complete the Comet Restart
Study, targeted for Q2 FY27, to consolidate the mine plan, execution requirements and
sequencing for the restart. Completion of the Study will provide the basis for
announcement of the preliminary restart mining schedule and key milestones toward
recommencement of operations.
Infrastructure delivery - advance the power, ventilation, pumping, accommodation,
safety and communications packages toward delivery, installation and commissioning,
with key infrastructure milestones targeted for Q2 FY27.
Underground drilling - complete the tender and contractor appointment process and
progress mobilisation for priority grade control and resource definition drilling targeted
to commence in Q2 FY27.
Site readiness - continue dewatering and targeted underground rehabilitation, and
complete the temporary workshop, pit ramp, site access and supporting site establishment
works.
Reedy drill programs - report further results from the Boomerang drilling program and
final results from the South Emu-Triton program.
The Company will provide further updates as material milestones are reached and the Comet
restart program advances toward commencement of mining.
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 8
Investor Relations
You can engage with the Company about this announcement here.
This announcement is authorised for release by the Board of Directors.
Enquiries:
Brendan Tritton
Managing Director & CEO
Investor Relations
communications@valiantgold.com.au
info@valiantgold.com.au
+61 8 6373 8900
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 9
About Valiant Gold
Valiant Gold is an emerging Western Australian gold company focused on unlocking value from proven
Murchison assets.
Demerged from Westgold Resources Limited (ASX: WGX) in March 2026, the Company holds 100% of the
Reedy and Comet gold projects, brownfields operations with historical production of more than 1Moz
and a combined 1.2Moz Mineral Resource. Both projects are located in the Murchison Province of Western
Australia.
With existing Mining Leases, a near-term pathway to production, a processing solution from day one and
a clear focus on mine restart and resource growth, Valiant is advancing toward its next phase of
development.
Current Mineral Resource Estimates1
are:
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
Comet 151,971 3.54 17,296 248,294 3.63 28,978 262,580 2.99 25,242 662,845 3.35 71,392
Comet North (OP) - - - 433,822 2.47 34,451 160,809 2.06 10,650 594,631 2.36 45,118
Comet North (UG) - - - 19,093 3.44 2,112 269,013 2.31 19,979 288,106 2.39 22,138
Pinnacles 84,012 2.22 5,996 1,189,880 2.28 87,223 955,172 2.34 71,860 2,229,064 2.31 165,549
Venus / Mercury - - - 249,588 1.5 12,037 50,769 1.67 2,726 300,357 1.53 14,775
Total 235,983 3.07 23,293 2,140,677 2.39 164,799 1,698,343 2.39 130,458 4,075,003 2.43 318,971
Boomerang - Kurara
(OP)
- -
292,071 0.91 8,536 1,711,352 1.50 82,312 2,003,423 1.41 90,847
Boomerang - Kurara
(UG)
- - 472,059 4.31 65,383 2,788,285 2.35 210,846 3,260,344 2.64 276,229
Calisto 1,112 2.21 79 147,196 2.31 10,932 29,863 1.21 1,162 178,170 2.13 12,173
Culculli - - - 76,092 1.23 3,009 185,572 1.48 8,830 261,664 1.41 11,839
Jack Ryan (UG) - - - 203,537 1.72 11,255 347,925 2.02 22,596 551,462 1.91 33,851
Midway - - - 42,828 1.39 1,914 9,273 1.11 331 52,101 1.34 2,245
Missing Link - - - 30,771 1.19 1,177 38,733 1.87 2,329 69,504 1.57 3,506
Rand (OP) - - - 662,275 1.43 30,448 556,841 2.5 44,757 1,219,116 1.92 75,255
Rand (UG) - - - 182,623 2.01 11,802 1,452,754 2.59 120,971 1,635,377 2.53 133,024
RL9 - - - 24,946 2.91 2,331 17,545 2.19 1,237 42,491 2.61 3,568
South Emu (UG) 16,815 3.61 1,952 676,953 3.78 82,161 725,403 4.47 104,227 1,419,172 4.13 188,350
Triton (UG) 46,690 3.31 4,967 244,799 3.86 30,411 4,694 3.17 478 296,183 3.77 35,862
Thompson's Bore - - - 98,741 1.61 5,111 98,741 1.61 5,111
Turn of the Tide - - - 265,542 1.32 11,269 151,032 1.17 5,681 416,574 1.27 17,009
West Zone - - - - - - 15,598 1.38 692 15,598 1.38 692
Total 64,617 3.37 6,998 3,321,692 2.53 270,629 8,133,611 2.34 611,559 11,519,920 2.4 889,561
Combined Total 300,600 3.13 30,291 5,462,369 2.48 435,428 9,831,954 2.35 742,017 15,594,923 2.41 1,208,532
Comet
Reedy
Measured Indicated Inferred Total
ASX ANNOUNCEMENT - COMET GOLD MINE RESTART ACTIVITIES ACCELERATE
2 SEPTEMBER 2026
pg. 10
Previous Disclosure and Competent Person’s Statement
This announcement is an operational update and does not report new Exploration Results, a new or
materially changed Mineral Resource Estimate or an Ore Reserve.
Information regarding the Mineral Resource Estimates is extracted from Valiant Gold Limited’s Prospectus
dated 16 February 2026, as amended by the Supplementary Prospectus dated 20 February 2026 (together,
the Prospectus). The Company confirms that it is not aware of any new information or data that materially
affects the information included in the Prospectus and that all material assumptions and technical
parameters underpinning the estimates in the Prospectus continue to apply and have not materially
changed. The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the Prospectus.
No Exploration Results are reported or discussed in this announcement.
Forward Looking Statements
This announcement includes various “forward-looking statements” with respect to, among other things,
goals, plans and strategies. Such forward-looking statements are not guarantees of future performance
and involve known and unknown risks, uncertainties and other factors beyond the control of the Company
that may cause actual results, performance and outcomes to differ materially from those expressed or
implied. Forward-looking statements are provided as a general guide only and should not be relied upon
as an indication or guarantee of future performance. Given these uncertainties, recipients are cautioned
not to place undue reliance on any forward-looking statement. Subject to any continuing obligations
under applicable law or the ASX Listing Rules, the Company disclaims any obligation to update or revise
any forward-looking statement to reflect a change in expectations, events, conditions or circumstances.