Comet Restart Advances Towards First Production in H2 FY27
Released
Released
Announcement PDF
Valiant Gold Limited (ACN 691 820 532)
A: Ground Floor, 34 Colin Street West Perth WA 6005 | W: www.valiantgold.com.au
ASX ANNOUNCEMENT
14 October 2026
COMET RESTART ADVANCES TOWARDS
FIRST PRODUCTION IN H2 FY27
Valiant Gold Limited (ASX: VAL) (Valiant or the Company) is pleased to report continued
progress on the restart of its 100%-owned Comet Gold Mine in Western Australia’s Murchison
region, with dewatering reaching 170 metres below surface and key site and underground
infrastructure now installed. First production remains targeted for H2 FY27
Key Highlights
Dewatering reaches the 1270 Level, 170 metres below surface, advancing access to the first
planned production areas
Core site facilities established, with the workshop, site offices and medical centre now
installed
Primary ventilation fans installed within budget and on schedule, with commissioning to
follow post establishment of site power
Power station works underway, with installation and commissioning to be completed by
the end of October 2026
Comet Restart Study on track for completion prior to end of Q2 FY27
Underground mining services tender progressing and drilling contractor appointment
nearing completion
First production remains targeted for H2 FY27
Management Comments
“Valiant has built strong momentum at Comet, with dewatering reaching 170 metres below
surface, core site facilities established and primary ventilation fans installed. These milestones
advance us towards first production, targeted for H2 FY27.
Our immediate priorities are to commission permanent site power, complete the Comet Restart
Study and finalise the underground mining and drilling contracts. We remain focused on delivering
each workstream safely, on schedule and within budget.
In parallel, underground drilling will support grade control, increase resource confidence and test
opportunities to extend mine life. With Comet funded to first production and further development
opportunities across our Murchison portfolio, Valiant is well positioned to create value beyond its
existing 1.2Moz Mineral Resource.”
Brendan Tritton, Managing Director & CEO
pg. 2
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Comet Overview
The Comet Gold Mine is located within Valiant’s Comet Gold Project in the Murchison region of
Western Australia, only 14 km by road from the Tuckabianna Mill and 110 km from the Bluebird
Mill, both of which are immediately accessible to Valiant under the ore purchase agreement with
Westgold Resources (Error! Reference source not found.). The Comet mine trend hosts an
existing Mineral Resource Estimate (MRE) of 3.77Mt @ 2.51g/t Au for 304koz of gold1
(Appendix
A), providing a strong foundation for the restart of underground mining operations.
Following successful underground re-entry in July 2026, inspections identified lower-than-
expected water levels, generally dry workings, serviceable infrastructure and limited
rehabilitation requirements in the first production zones. These findings have informed the site
establishment, dewatering, rehabilitation, engineering and mine planning activities now
underway.
Figure 1: Location of the Comet Project relative to regional processing infrastructure, including facilities
contemplated under the Ore Purchase Agreement with Westgold Resources.¹
1
Refer to the Company’s Prospectus dated 16 February 2026, as amended by the Supplementary Prospectus dated 20 February
2026 (together, the Prospectus) for further information regarding the Mineral Resource Estimates.
pg. 3
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Comet Operational Update
Dewatering Update
Dewatering is progressing across two fronts, with the initial Pinnacles dewatering program,
which will provide access to the first production area, targeted for completion prior to the end
of Q2 FY27. Dewatering of the Comet decline, to provide access to the deeper parts of the mine,
is anticipated to be completed during the second half of FY27.
The water level at Comet and Pinnacles currently stands at the 1270 Level or 170m below surface
(see Figure 2). Dewatering of the Comet and Pinnacles underground workings continues to
progress, with water being pumped from the workings and discharged into the Eclipse Pit
(Figure 3). The Eclipse and Comet North pit voids provide sufficient storage capacity across the
project to accommodate the expected volumes of water to be removed from the underground.
Pumping is being undertaken using the interim equipment previously mobilised to site,
operating through the new discharge line installed from the pit floor to surface. Installation of
the permanent dewatering network continues in parallel, with the permanent pumping
equipment to be commissioned in conjunction with the establishment of permanent site power
in Q2 FY27.
Figure 2: Comet Mine schematic cross-section showing the underground mine workings, Mineral Resource
Estimate outline and classifications, planned drill platforms, and priority grade control, resource conversion
and resource extension drilling areas.¹
pg. 4
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Figure 3: Water discharging into the Eclipse Pit from the Comet underground dewatering operation.
Workshop, Offices and Medical Centre
The workshop, site offices and medical centre have now been installed at the Comet project
(Figure 4). Completion of these facilities follows the pad preparation, levelling, and supporting
water infrastructure works and establishes the initial core surface facilities required to support
the restart program.
The workshop provides on-site maintenance and servicing capability for equipment engaged in
dewatering, rehabilitation and site establishment activities, reducing reliance on off-site support.
The site offices accommodate the technical, planning and supervisory personnel now based at
Comet, and the medical centre establishes on-site emergency response and medical capability
consistent with the requirements of an active work site.
Together, these facilities allow a progressive increase in site activity and workforce numbers as
the restart program advances and will operate alongside the initial 30-person accommodation
camp scheduled for delivery in November 2026.
pg. 5
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Figure 4: Workshop, office and medical facilities installed at Comet.
Power Station
Initial layout and preparatory works for the 6.1 MW power station are progressing, including
upgrades to the earthing system and preparation of the generator compound. These works will
support the planned installation and commissioning of the power station by the end of October
2026.
pg. 6
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Primary Ventilation Fans
Primary ventilation fans have been installed in both the Comet and Pinnacles underground
workings, completing a key element of the underground infrastructure program. The installation
covers the two separate underground ventilation circuits and follows the delivery of the fan
equipment and associated installation accessories.
Installation was undertaken following assessment of the existing underground ventilation
infrastructure and the interfaces required for the new equipment. Commissioning activities are
progressing, with the fans to be brought into full service in conjunction with the establishment
of the site power station.
Figure 5: Primary ventilation fan installation at the Pinnacles underground workings.
pg. 7
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Comet Restart Study
Mine engineering, design and planning activities continue to progress on schedule, in parallel
with the infrastructure, site and technical workstreams required to return Comet to production.
The Comet Restart Study remains targeted for completion in Q2 FY27 and will consolidate the
mine plan, execution requirements and sequencing for the restart, incorporating the outcomes
of the infrastructure, procurement, dewatering and site activities now underway.
Completion of the Study will provide the basis for the Company to announce a preliminary
restart mining schedule outlining the key milestones, indicative sequencing and anticipated
timing toward recommencement of operations.
Underground Mining Services Contract
The tender evaluation process for the underground mining services contract is progressing. The
contract will cover underground development and production activities required to deliver the
Comet restart, and the scope has been developed in conjunction with the mine planning and
engineering work being undertaken as part of the Comet Restart Study. A decision will be made
and communicated to the market in relation to the selected mining contractor in Q2 FY27.
Underground Drilling Contract
Valiant has completed the tender process and is in the final stages of appointing an
underground diamond drilling contractor to undertake priority grade control and resource
definition drilling programs (Figure 2). Mobilisation to the Comet Mine is expected in Q2 FY27.
The underground drilling program represents a critical step in advancing the Comet Mine, with
drilling aimed at increasing resource confidence, identifying opportunities for resource growth,
and supporting mine life extension. Appointment of the drilling contractor will enable Valiant to
expedite these organic value-generating activities.
Looking Forward
Key activities targeted for Q2 FY27 include:
Installation and commissioning of the site power station
Completion of the Comet Restart Study and preliminary restart mining schedule
Appointment of the underground mining services contractor
Delivery and mobilisation of the initial 30-person accommodation camp
Appointment and mobilisation of the underground drilling contractor
Commencement of priority grade-control and resource-definition drilling
Valiant will also continue to report results from the ongoing Boomerang resource drilling
program.
pg. 8
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Valiant’s Development Pipeline
Comet: Lead mine restart workstream, with critical infrastructure, site establishment,
dewatering, rehabilitation and technical activities advancing in parallel with completion of
the Comet Restart Study and development of the preliminary restart mining schedule.
South Emu–Triton: Future underground restart opportunity, with recent drilling advancing
mine planning and detailed dewatering preparations underway ahead of restart.
Boomerang: Potential open-pit and underground development opportunity, with Resource
definition drilling underway and Resource-growth planning in progress.
No development decision has been made in respect of Boomerang or South Emu–Triton. Any future dewatering or development decision
will remain subject to technical review, approvals, funding, sequencing and other relevant considerations.
Investor Relations
You can engage with the Company about this announcement here.
This announcement is authorised for release by the Board of Directors.
Enquiries:
Brendan Tritton Investor Relations
Managing Director & CEO communications@valiantgold.com.au
info@valiantgold.com.au
+61 8 6373 8900
pg. 9
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
About Valiant Gold
Valiant Gold is a Western Australian gold company advancing a fully funded mine restart in the Murchison
region. Demerged from Westgold Resources and listed in March 2026, the Company holds 100% of the
Comet and Reedy gold projects: brownfields assets on granted Mining Leases with existing underground
development, historical production exceeding 1Moz, and a combined Mineral Resource of 1.2Moz @
2.4g/t Au.
An Ore Purchase Agreement with Westgold Resources also secures processing capacity at the
Tuckabianna and Bluebird mills, removing the requirement to construct a standalone plant thus
establishing a lower-capital pathway to production, targeted for H2 FY27.
With existing Mining Leases, a near-term pathway to production, a processing solution from day one and
a clear focus on mine restart and resource growth, Valiant is advancing toward its next phase of
development.
Current Mineral Resource Estimates1
are:
Competent Person’s Statement
The information regarding the Mineral Resource estimates is extracted from Valiant Gold Limited’s
Prospectus dated 16 February 2026, as amended by the Supplementary Prospectus dated 20 February
2026 (together, the Prospectus). The Company confirms that it is not aware of any new information or
data that materially affects the information included in the Prospectus and that all material assumptions
and technical parameters underpinning the estimates in the Prospectus continue to apply and have not
materially changed. The Company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the Prospectus.
No Exploration Results are reported or discussed in this announcement.
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
Comet 151,971 3.54 17,296 248,294 3.63 28,978 262,580 2.99 25,242 662,845 3.35 71,392
Comet North (OP) - - - 433,822 2.47 34,451 160,809 2.06 10,650 594,631 2.36 45,118
Comet North (UG) - - - 19,093 3.44 2,112 269,013 2.31 19,979 288,106 2.39 22,138
Pinnacles 84,012 2.22 5,996 1,189,880 2.28 87,223 955,172 2.34 71,860 2,229,064 2.31 165,549
Venus / Mercury - - - 249,588 1.5 12,037 50,769 1.67 2,726 300,357 1.53 14,775
Total 235,983 3.07 23,293 2,140,677 2.39 164,799 1,698,343 2.39 130,458 4,075,003 2.43 318,971
Boomerang - Kurara
(OP)
- -
292,071 0.91 8,536 1,711,352 1.50 82,312 2,003,423 1.41 90,847
Boomerang - Kurara
(UG)
- - 472,059 4.31 65,383 2,788,285 2.35 210,846 3,260,344 2.64 276,229
Calisto 1,112 2.21 79 147,196 2.31 10,932 29,863 1.21 1,162 178,170 2.13 12,173
Culculli - - - 76,092 1.23 3,009 185,572 1.48 8,830 261,664 1.41 11,839
Jack Ryan (UG) - - - 203,537 1.72 11,255 347,925 2.02 22,596 551,462 1.91 33,851
Midway - - - 42,828 1.39 1,914 9,273 1.11 331 52,101 1.34 2,245
Missing Link - - - 30,771 1.19 1,177 38,733 1.87 2,329 69,504 1.57 3,506
Rand (OP) - - - 662,275 1.43 30,448 556,841 2.5 44,757 1,219,116 1.92 75,255
Rand (UG) - - - 182,623 2.01 11,802 1,452,754 2.59 120,971 1,635,377 2.53 133,024
RL9 - - - 24,946 2.91 2,331 17,545 2.19 1,237 42,491 2.61 3,568
South Emu (UG) 16,815 3.61 1,952 676,953 3.78 82,161 725,403 4.47 104,227 1,419,172 4.13 188,350
Triton (UG) 46,690 3.31 4,967 244,799 3.86 30,411 4,694 3.17 478 296,183 3.77 35,862
Thompson's Bore - - - 98,741 1.61 5,111 98,741 1.61 5,111
Turn of the Tide - - - 265,542 1.32 11,269 151,032 1.17 5,681 416,574 1.27 17,009
West Zone - - - - - - 15,598 1.38 692 15,598 1.38 692
Total 64,617 3.37 6,998 3,321,692 2.53 270,629 8,133,611 2.34 611,559 11,519,920 2.4 889,561
Combined Total 300,600 3.13 30,291 5,462,369 2.48 435,428 9,831,954 2.35 742,017 15,594,923 2.41 1,208,532
Comet
Reedy
Measured Indicated Inferred Total
pg. 10
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Forward Looking Statements
This announcement includes various ‘forward-looking statements’ with respect to, among other things,
goals, plans, and strategies. Such forward-looking statements are not guarantees of future performance
and involve known and unknown risks, uncertainties and other factors beyond the control of the Company
that may cause the actual results, performance and outcomes to be materially different from those
expressed or implied by such statements. Forward-looking statements are provided as a general
guide only, and should not be relied on as an indication or guarantee of future performance. Given these
uncertainties, recipients are cautioned to not place undue reliance on any forward-looking statement.
Subject to any continuing obligations under applicable law, the Company disclaims any obligation or
undertaking to disseminate any updates or revisions to any forward-looking statements in this
announcement to reflect any change in expectations in relation to any forward-looking statements or any
change in events, conditions or circumstances on which any such statement is based.
pg. 11
ASX ANNOUNCEMENT – COMET RESTART ADVANCES TOWARDS FIRST PRODUCTION IN H2 FY27
14 October 2026
Appendix A – Comet Mine Trend Long Section
Comet Mine Trend schematic long section, facing west, showing the Mineral Resource Estimate, ounce-per-vertical-metre
distribution and previously mined volumes. ¹